Sneaking in a quick post

February 21, 2008   

I have no time for a real update, just a quick one.

Here’s the kitchen timeline so far:

Last week
Thursday: Demo
Friday: Start electrical work
Saturday (they came in because they wanted to resolve the wiring issues): Do more electrical work

This week
Monday: holiday
Tuesday: Finish eletrical and plumbing — we put in insulation Monday night and that night
Wednesday: Start drywall — everything that goes behind cabinets is taped and plastered
Thursday: tape & plaster remaining walls, drywall part of diningroom as a bonus, start putting cabinets in — they say they will be done w/ almost all of the cabinets today
Friday: sand and plaster remaining walls
Monday: mystery?

We need to decide on a sink by tomorrow morning! Egads. Things are going at a breakneck speed. It is both exhilarating and a bit much.

My work is also going at such a speed. And I feel the same about it as I do about the kitchen.